The Integrated Pipeline is a joint water supply project between Dallas Water Utilities and Tarrant Regional Water District. It involves building 150 miles of pipeline to transport up to 350 million gallons water daily from three East Texas Reservoirs into the Metroplex to increase reliable water access. The project recently reached a new milestone when the new tunnel under Trinity River was completed. Workers are now beginning to add 50‐foot sections of 108‐inch diameter steel pipe.

Stiver Engineering performed full design work for the IPL tunnel. The design/build project scope included construction of approximately 3,802 linear feet of 108‐inch water line including 2,614 linear feet of tunnel under the Trinity River and the remainder in deep open cut segments along the proposed alignment of Section 17.

Other aspects include tunnel launch and retrieval portals/shafts, deep open cut approach ramps with temporary shoring at approximately 12:1 slope, pipe laying within approach ramps and tunnel initial support, pipe encasement with flowable fill and reinforced concrete, tunnel grouting, a 15.6‐foot diameter custom designed tunnel boring machine, and precast segmental tunnel lining.

The new TxDOT bridge will replace the existing truss bridge over the Colorado River in Columbus, Texas.  Stiver Engineering provided construction consulting to the bridge contractor with cofferdam designs for crane access on both banks of the Colorado River.  The cofferdams allowed the crane to get closer to the center of the proposed bridge so that the bridge beams could be lifted and installed.  The cofferdam was constructed using driven sheet piles, wales and cross ties.