As part of a 108-inch transmission waterline project along Esplanade Boulevard between Imperial Valley Drive and Green Plaza in Houston, Stiver Engineering provided a custom lifting plan for the bottom elbow of the waterline at one of our shaft designs. The fitting had to be lifted and held in place while it was welded to the carrier pipe in the tunnel.

Stiver Engineering provided shoring design services for a 72-inch water line project from Emancipation Avenue to Tuam Street on Clay Street in Houston, Texas. Stiver’s work included secant pile shaft design for the launch and receiving shafts. The shafts are 34 ft ID and 80 ft deep. We also created designs for the breakout structure for the Akkerman TBM.

Stiver Engineering provided a shoring design for the launch and receiving tunnel shafts, including portal design implementing soldier piles and the shaft design implementing sheet piling and wale sets. Calculations and a finite element analysis (FEA) were performed for a 108-inch diameter tunnel steel casing pipe. Calculations for grout pressure used to fill voids outside the casing pipe were also provided.

Stiver Engineering provided launch shaft, excavator digger shield and thrust block design services for a 108-inch-diameter water line project along city easements from Milner Road to Aldine Westfield Road in Houston, Texas, near the Intercontinental Park area. Two shoring pits, each more than 30 feet deep, were designed with soldier piles, steel plates and timber lagging. Waler beams were used to support the soldier piles. At the launch pit, a jacking frame was designed at the bottom of the pit to resist the thrust from the excavator boring shield system. The jacking frame consisted of three extra waler sets and diagonal bracings connected to a portal support frame using king beams, a header beam and a footer beam.

Stiver Engineering provided sheet pile shoring for the installation of beach vaults for the Big Wave Project in Diego Garcia, British Indian Ocean Territory. The site had hard corals located 13 feet below natural ground, so we created two alternatives for the shoring pit. The first alternative was a cantilever shoring system consisting of 14-foot and 30-foot-long piles with staggered embedment. The second was a braced shoring system designed to accommodate the client’s concern of not being able to embed the sheet piles more than 6 inches into the hard coral. Material was limited on the island, so Stiver proposed a custom wale set consisting of channels and pipes.